Development of the project for the creation of social services infrastructure

20.08.2020

Projects

Since February of that year, THE ERDF project of the municipality of Rezekne IS 9.3.1.1/19/I/047 “Establishment and development of infrastructure-based social service infrastructure in Rezekne municipality”.
The aim of the project is to establish a society-based social service provision infrastructure for adult persons with mental disorders and children with functional disorders in the territory of Rezekne municipality, based on the infrastructure development solutions specified in the Latgale Planning Region deinstitutionalisation plan (2017-2020).
As a result of the implementation of the project, two social service locations will be established in the territory of the municipality, performing the following activities:
1) the creation of a group apartment house for persons with mental disorders IN Dricānu parish Pilcene - the conversion of a one-storey administrative building into a group apartment house (8 places), construction of construction works and fitting of premises with material technical provision will be performed;
2) Establishment OF a multifunctional social service centre “Vecružina” IN Silmalas parish Vecružin - construction works of the building environment shall be performed in the right wing of the building of the building of the building Those children's house in three floors, the construction of construction works and the fitting of premises with material provision for the establishment of a social rehabilitation service centre for children with functional disorders, “breathlessness” service in children with functional disorders (6 places) and a day care centre for children with functional disorders (10 places).
The total budget of the project is 597 936,00 EURO eligible costs, of which ERDF funding is 508 245.60 EURO, State budget grant - 26 907,12 EURO, municipal co-financing - 62 783.28 EURO.
Duration of the project: 18 months: 1 February 2020 to 31 July 2021.
In the month of August of that year, construction works are ongoing in Pilcene, where Rezekne municipality, in the territory of the “Pilcene” branch of the old folk house, rebuilds the local building firm SIA “Rezekne Construction Service” into the local government's one-storey building for the group apartment house (see photo). The dismantling works, the heat insulation of the cap, the construction of windows, the work of doors, walls and ceilings, and the construction work of the doors, sewerage, ventilation, heating, electrical supply etc. are already fully carried out.
Since the beginning of April, construction works have also been started in Vecružin, where SIA “Rēzekne Construction Service” in three-storey building – Tiskad in the right wing of the building of the children's house – adjusts the premises for the provision of social services to children with functional disorders. In the month of August, almost entirely dismantling works were carried out, the interior finishing works and the construction of the elevator shaft.
Construction works in both Pilcene and Vecrujin are planned to be completed in December 2020.
In the picture: the top group apartment building in Pilcene.
Brigita Arbidane, project manager in the municipality of Rezekne