Updates of the project for the creation of social services infrastructure

logo
Since February of that year, THE ERDF project of the municipality of Rezekne IS 9.3.1.1/19/I/047 “Establishment and development of infrastructure-based social service infrastructure in Rezekne municipality”.
The aim of the project is to establish a society-based social service provision infrastructure for adult persons with mental disorders and children with functional disorders in the territory of Rezekne municipality, based on the infrastructure development solutions specified in the Latgale Planning Region deinstitutionalisation plan (2017-2020).
As a result of the implementation of the project, two social service locations will be established in the territory of the municipality, performing the following activities:
1) the creation of a group apartment house for persons with mental disorders IN Dricānu parish Pilcene - the conversion of a one-storey administrative building into a group apartment house (8 places), construction of construction works and fitting of premises with material technical provision will be performed;
2) Establishment OF a multifunctional social service centre “Vecružina” IN Silmalas parish Vecružin - construction works of the building environment shall be performed in the right wing of the building of the building of the building Those children's house in three floors, the construction of construction works and the fitting of premises with material provision for the establishment of a social rehabilitation service centre for children with functional disorders, “breathlessness” service in children with functional disorders (6 places) and a day care centre for children with functional disorders (10 places).
The total budget of the project is 597 936,00 EURO eligible costs, of which ERDF funding is 508 245.60 EURO, State budget grant - 26 907,12 EURO, municipal co-financing - 62 783.28 EURO.
Duration of the project: 18 months: 1 February 2020 to 31 July 2021.
In May, active construction works in Pilcene, where the municipality of Rezekne is located in the territory of the “Pilcene” branch of the old folk house, the local building company SIA “Rezekne Construction Service” rebuilds the local government's one-storey building on the group apartment house. The 20 th Mayan has already been fully dismantled, the heat insulation of the cap, the construction of windows, the partially performed work of the mounting and preparation of doors, walls and ceilings, the construction works of water-operated, sewerage, ventilation, heating, power supply etc.
Since the beginning of April, construction works have also been started in Vecružin, where SIA “Rezekne Construction Service” in three-storey building – in the right wing of the Tiskada Children's House - will be adapted to provide social services for children with functional disorders. In the month of May, almost entirely dismantling works have been carried out and internal finishing works are started, the construction of the elevator bases is being carried out.
Construction works in both Pilcene and Vecrujin are planned to be completed in December 2020.
Project manager in the municipality of Rezekne: